Utility Impacts/Shutdowns
- Phase 1 – Supplemental Utility Plant
- Engineering Classroom and Research Building (ECRB)
- Phase 2 – New training ship dock
Utility Impact Calendar
Dates are subject to change (weather, availability of materials, etc.). Please monitor your campus email for Aggnews updates.
Dates | Utility | Status | Impacted Buildings | Project |
---|---|---|---|---|
5/14/2024 | Electric | Complete | 3027 - PMEC, 3104 - Wetland Center | ECRB |
5/21-22/2024 | Electric | Postponed | 3003 - Waterfront Operations, Clipper Dock, NOAA Dock, T-Head Fishing Pier, Lifeboat Davit | ECRB |
5/18/2024 | Sanitary Sewer | Postponed | No impacts | ECRB |
5/22/2024 | Natural Gas | Postponed | 3004 - Northen Student Center, 3005A - Hullabaloo Hall, 3005B - Oceans Hall, 3006 - Facilities Services, 3007 - CLB, 3018 - PE Facility, 3027 - PMEC, 3028 - Clubhouse, 3029 - OCSB, 3030 - Seibel Student Services Building, 3034 - Main, 3035 - ASEC | ECRB, Supplemental Utility Plant |
6/8/2024 | Domestic Water (drinking, showers) | On schedule | 3001 - Kirkham Hall, 3002 - Old Engineering, 3003 - Waterfront Operations, 3006 - Facilities Services, 3027 - PMEC | ECRB |