Utility Impacts/Shutdowns    

  • Phase 1 – Supplemental Utility Plant
  • Engineering Classroom and Research Building (ECRB)
  • Phase 2 – New training ship dock

Utility Impact Calendar


Dates are subject to change (weather, availability of materials, etc.). Please monitor your campus email for Aggnews updates.

Dates Utility Status Impacted Buildings Project
5/14/2024 Electric Complete 3027 - PMEC, 3104 - Wetland Center ECRB
5/21-22/2024 Electric Postponed 3003 - Waterfront Operations, Clipper Dock, NOAA Dock, T-Head Fishing Pier, Lifeboat Davit ECRB
5/18/2024 Sanitary Sewer Postponed No impacts ECRB
5/22/2024 Natural Gas Postponed 3004 - Northen Student Center, 3005A - Hullabaloo Hall, 3005B - Oceans Hall, 3006 - Facilities Services, 3007 - CLB, 3018 - PE Facility, 3027 - PMEC, 3028 - Clubhouse, 3029 - OCSB, 3030 - Seibel Student Services Building, 3034 - Main, 3035 - ASEC ECRB, Supplemental Utility Plant
6/8/2024 Domestic Water (drinking, showers) On schedule 3001 - Kirkham Hall, 3002 - Old Engineering, 3003 - Waterfront Operations, 3006 - Facilities Services, 3027 - PMEC ECRB